Lakota Interim Digester - Award Construction

980 Willeys Lake Rd
Go to content

Main menu:

Lakota Interim Digester

Select Projects
  • Owner: Lakota Water & Sewer Dist.

  • Contract Amount: $300,000

  • Start Date: July 2018

  • Completed: December 2018

Award's team worked at the Lakota Wastewater Treatment plant to upgrade their digester. The work included new piping, pipe supports, installation of owner-furnished pumps and flow meters and the replacement of existing temporary pump control panels.  

 
Back to content | Back to main menu