Seattle Pump Station Upgrades

Select Projects
  • Owner: City of Seattle

  • Contract Amount: $2.4 mill

  • Start Date: January 2019

  • Completed: Sept. 2019

Award worked for Seattle Public Utilities along with Miller Sheet Metal and Sundancer Electric to perform ventilation upgrades to 25 pump stations spread out throughout the City. The work required careful logistical management, excavation in tight spaces, coatings, modifications to existing ducting, and associated HVAC and electrical work. That careful management allowed the project to be completed safely and over 2 months ahead of schedule.

 